ebooksgratis.com

See also ebooksgratis.com: no banners, no cookies, totally FREE.

CLASSICISTRANIERI HOME PAGE - YOUTUBE CHANNEL
Privacy Policy Cookie Policy Terms and Conditions
East Side Access - Wikipedia, the free encyclopedia

East Side Access

From Wikipedia, the free encyclopedia

A Future East Side Access Station.
A Future East Side Access Station.

East Side Access is a public works project being undertaken by the Metropolitan Transportation Authority (MTA) in New York City, designed to bring the Long Island Rail Road (LIRR) into a new East Side station to be built below and incorporated into Grand Central Terminal in Manhattan.

Contents

[edit] Purpose

Access to the East Side of Manhattan has long been a dream of LIRR riders who work on the East Side but must now commute into the Long Island Rail Road's sole current Manhattan stop at the congested Pennsylvania Station, on the West Side. A 1998 study showed that only 36% of all jobs in Midtown are within walking distance of Pennsylvania Station, while almost 70% are within walking distance of Grand Central Terminal, the other major Manhattan rail terminal. (There is some overlap, and some jobs are not within walking distance of either facility.) Direct service to the East Side would allow many riders to walk to work and allow other riders to reduce the number of subway and bus transfers they must make in order to reach their jobs, shortening and simplifying their commutes and cutting up to 40 minutes off their daily travel time. The addition of a new Manhattan terminal will also increase capacity on the LIRR as a whole.

The new LIRR East Side station under Grand Central Terminal will offer new entrances, a concourse, eight tracks on four platforms lower than the existing Metro-North lower level tracks, and a mid-level mezzanine. This new station would allow easier transfers for commuters travelling between Long Island on the Long Island Railroad, Metro-North Railroad destinations (in the Bronx, Westchester County, the Hudson Valley, and Connecticut), and the New York City Subway. The new terminal will increase the number of tracks at Grand Central from 67 to 75. The terminal will be reached by high-rise escalators.

Initially the East Side Access (ESA) project was supposed to reduce congestion at Penn Station and allow Metro-North (MNR) to offer train service to that station via the old New York Central West Side Line and the New York, New Haven and Hartford RR's Hell Gate Line, both currently used only by Amtrak. However, due to ridership growth on the LIRR, the ESA project will simply add critically needed capacity for the LIRR. MNR still plans to offer service to Penn Station, but will likely wait until New Jersey Transit completes its Trans-Hudson Express Tunnel project, which - though significantly increasing New Jersey Transit traffic between New Jersey and New York City - will also expand Penn Station.

[edit] Route and service level

East Side Access route & completion thru April 2008
East Side Access route & completion thru April 2008

Extending between Sunnyside, Queens, and Grand Central Terminal, the East Side Access project will route the LIRR from its Main Line through new track connections in Sunnyside Yard and through the lower level of the existing 63rd Street Tunnel under the East River. In Manhattan, a new tunnel will begin at the western end of the 63rd Street Tunnel at Second Avenue, curving south under Park Avenue and entering a new LIRR terminal beneath Grand Central Terminal.

Current plans call for 24-trains-per-hour service to Grand Central Terminal during peak morning hours, with an estimated 162,000 passenger trips to and from Grand Central on an average weekday. Connections to AirTrain JFK at Jamaica Station in Jamaica, Queens, will facilitate travel to John F. Kennedy International Airport from the East Side of Manhattan.

A new LIRR train station in Sunnyside at Queens Boulevard and Skillman Avenue[1] along the LIRR’s Main Line (into Penn Station) will provide one-stop access for area residents to Midtown Manhattan.[2] The station may spur economic development and growth in Long Island City.

[edit] Construction History and Progress

Construction of the line to Grand Central was begun in November 1969 (see IND 63rd Street Line) as the lower level of a cut-and-cover project to build the New York City Subway's 63rd St Line. The MTA's contractor floated premanufactured four-chamber tunnel boxes into place in the East River and sank them to create the East River crossings for the subway and the LIRR. After a long delay caused by New York City's fiscal collapse of the 1970s, the 63rd St subway line and LIRR tunnel were completed as far as 21 St in Long Island City. Between 1995 and 2001, the 63rd St subway line was connected to the Queens Blvd. corridor, and the LIRR tunnel was extended under 41 Avenue in Queens to the west side of Northern Blvd. The western end of this tunnel sat under Second Avenue at 63 Street.

The current East Side Access Project represents the construction effort to complete the line to Grand Central Terminal. After voters in New York approved a bond issue to provide state funds to the project, the federal government committed to provide $2.6 billion to help build the East Side Access project by signing a Full Funding Grant Agreement (FFGA) in December 2006.[3] The construction contract for a one-mile tunnel in Manhattan west and southward from the long dormant lower level of the 63rd Street rail tunnel to the new station beneath Grand Central terminal was awarded on July 13, 2006, to Dragados/Judlau, a joint American-Spanish venture (the American company is located in College Point, Queens, NY).[4] The total contract award is $430 million contract,[4] and is utilizing two large tunneling devices owned by the Spanish firm.[5]

Judlau created a launch chamber for Tunnel Boring Machines under Second Avenue at 63rd St using a controlled drill-and-blast method, then assembled and launched each machine. The first TBM was launched west and southbound from the 63rd Street tunnel in September of 2007; the second machine began boring a parallel tunnel in December 2007. After boring is complete, the TBMs will be backed out of the tunnels and cast-in-place concrete sections placed to create the lining.[6] Each tunnel will be 22 feet in diameter and carry trains 140 feet beneath street level.[7] The TBMs bore an average of 50 feet per day and are expected to complete the twin tunnels by the summer of 2008. Cross-connections between the tunnels will be created by controlled drill-and-blast.

In Queens, Pile Foundation Construction Company is building an $83 million open-cut and deck project, which is extending the tracks under Northern Blvd into Sunnyside Yard, and creating an area that serves as both the launch chamber for soft-bore Queens tunnels, connecting the 63rd St line to the main LIRR branches, and an interlocking and emergency exit and venting facility.[8].[9] Perini Corporation was awarded a $161 million contract to reconfigure Harold Interlocking, increasing its capacity to accommodate Grand Central-bound trains and accept new yard lead tracks to allow trains to enter the storage yards. On February 15, 2008, MTA awarded Dragados-Judlau a $499 million contract to excavate the LIRR station cavern, track wye caverns.

[edit] Cost Inflation and Community Impact

The East Side Access project cost has increased from $3 billion in 1998[citation needed] to US$6.3 billion in 2006.[4] Construction work is ongoing and a 2013 completion date is projected. and elevator/escalator shaft areas.[10]

Given the massive size of the project, the plan has aroused concerns and opposition. In 2005, businesses and Edward Cardinal Egan began to express concerns about the tunneling process. Egan in particular is concerned about the impact on St. Patrick's Cathedral, which faces Fifth Avenue with its back on Madison Avenue north of 50th Street. The project is proposing that an air vent be placed south of 50th Street and east of Madison Avenue, just outside the existing trainshed.[11]

[edit] Side effects

East Side Access is likely to affect commuting patterns in Manhattan and put greatly increased passenger loads on the already overcrowded IRT Lexington Avenue Line, the sole East Side subway line, as well as on surface bus routes on the East Side. The project has, therefore, focused attention on the long-delayed Second Avenue Subway along the far East Side of Manhattan, which is now under construction. It is expected to relieve north/south commuting pressure emanating from Grand Central Terminal.

At the same time, East Side Access will reduce the load on morning northbound rush-hour E service between Pennsylvania Station and Midtown East.

[edit] References

  1. ^ Chapter 2: Project Alternatives (PDF). East Side Access - Final Environmental Impact Statement 2-20:2-21. Federal Transit Administration and the Metropolitan Transportation Authority of the State of New York, in cooperation with the MTA Long Island Rail Road (March 2001). Retrieved on 2008-02-15. “The station's main entrance would be at street level on the west side of the Queens Boulevard bridge near its Skillman Avenue end, directly above the center platform.”
  2. ^ Vandam, Jeff. "An Enclave at Once Snug and Inclusive", The New York Times, February 4, 2007. Accessed February 14, 2008. "When the Long Island Rail Road’s East Side Access project is completed in 2013, its trains, too, will go to Grand Central. Sunnyside’s new station in the system will create a nonstop commute to Midtown."
  3. ^ United States Department of Transportation (2006-12-18). "U.S. Transportation Secretary Signs Record $2.6 Billion Agreement to Fund New Tunnel Network To Give Long Island Commuters Direct Access to Grand Central Station". Press release. Retrieved on 2007-01-18.
  4. ^ a b c MTA Takes Major Step Towards Completing East Side Access Plan, NY1, July 12, 2006
  5. ^ MTA Capital Construction - Procurement
  6. ^ MTA's Official East Side Access Project Page
  7. ^ [1]
  8. ^ MTA East Side Access Work Underway
  9. ^ New York's Subway System Finally Starting Major Expansion, newyork.construction.com, May 2006 issue
  10. ^ MTACC Procurement
  11. ^ East Side Access Draws Opponents, New York Sun, February 10, 2005

[edit] External links


aa - ab - af - ak - als - am - an - ang - ar - arc - as - ast - av - ay - az - ba - bar - bat_smg - bcl - be - be_x_old - bg - bh - bi - bm - bn - bo - bpy - br - bs - bug - bxr - ca - cbk_zam - cdo - ce - ceb - ch - cho - chr - chy - co - cr - crh - cs - csb - cu - cv - cy - da - de - diq - dsb - dv - dz - ee - el - eml - en - eo - es - et - eu - ext - fa - ff - fi - fiu_vro - fj - fo - fr - frp - fur - fy - ga - gan - gd - gl - glk - gn - got - gu - gv - ha - hak - haw - he - hi - hif - ho - hr - hsb - ht - hu - hy - hz - ia - id - ie - ig - ii - ik - ilo - io - is - it - iu - ja - jbo - jv - ka - kaa - kab - kg - ki - kj - kk - kl - km - kn - ko - kr - ks - ksh - ku - kv - kw - ky - la - lad - lb - lbe - lg - li - lij - lmo - ln - lo - lt - lv - map_bms - mdf - mg - mh - mi - mk - ml - mn - mo - mr - mt - mus - my - myv - mzn - na - nah - nap - nds - nds_nl - ne - new - ng - nl - nn - no - nov - nrm - nv - ny - oc - om - or - os - pa - pag - pam - pap - pdc - pi - pih - pl - pms - ps - pt - qu - quality - rm - rmy - rn - ro - roa_rup - roa_tara - ru - rw - sa - sah - sc - scn - sco - sd - se - sg - sh - si - simple - sk - sl - sm - sn - so - sr - srn - ss - st - stq - su - sv - sw - szl - ta - te - tet - tg - th - ti - tk - tl - tlh - tn - to - tpi - tr - ts - tt - tum - tw - ty - udm - ug - uk - ur - uz - ve - vec - vi - vls - vo - wa - war - wo - wuu - xal - xh - yi - yo - za - zea - zh - zh_classical - zh_min_nan - zh_yue - zu -