Biglow Canyon Wind Farm
From Wikipedia, the free encyclopedia
Biglow Canyon Wind Farm is an electricity generating wind farm facility located in Sherman County, Oregon, United States. It is owned by Portland, Oregon, based Portland General Electric and began operations in 2007. Biglow has a generating capacity of 125 megawatts. It is located roughly five miles northeast of Wasco, Oregon[1] and about ten miles (16 km) southeast of Rufus, Oregon. Biglow covers 25,000 acres (100 km²) in the Columbia River Gorge.
Contents |
[edit] History
In 2005, Orion Energy announced plans to develop a 450 megawatt wind farm with 225 turbines at Biglow Canyon in the Columbia River Gorge, at the time the largest project of its kind in Oregon.[2] Portland General Electric (PGE) acquired Orion’s development right to the $200 million project in 2006.[3] In November 2006, PGE purchased the first 76 turbines for the project from Vestas, with the project cost increasing to an estimated $256 million for the first phase.[4] PGE broke ground on the site in February 2007. In the middle of October 2007, ten Vestas V82 wind turbines were energized to produce the first electricity at Biglow.[5] The last of the 76 turbines in the first-phase of the wind farm development became operational in December 2007.[6] The turbines for phase 2 and 3 have been ordered from Siemens Energy. There will be one hundred and forty-one SWT-2.3-93 turbines with a capacity of 2.3 MW each.[7]
[edit] Operations
The Biglow Canyon Wind Farm has an installed capacity of 125 megawatts. Additional phases, planned for construction in 2009 and 2010, are expected to bring its total generating capacity to between 400 and 450 megawatts.[6] The site covers 25,000 acres (100 km²) in Sherman County.[5] The wind farm uses a feeder transmission line from the canyon to high-voltage transmission lines via a power substation located near The Dalles.[5][8] PGE does not own this line. Additionally, the line connects this and other wind farms to the Bonneville Power Administration run power grid built for use with the hydroelectric dams on the Columbia River.[5]
[edit] Certification
The facility is authorized to install up to 225 wind turbines totaling 450 MW and averaging 150 MW distributed over 25,000 acres (100 km²). Each turbine's supporting tower must be between 265 and 280 feet (80-85 m) tall; combined with windmill blades, each unit may be from 400 to 445 feet (122-136 m) tall. The turbines may be aligned in up to 30 corridors 500 feet (150 m) wide on private farmland leased from the appropriate landowners.[1]
The initial construction—termed phase I—provides a completed capacity of 125 MW or enough to power 34,000 homes.[9] Phase I is expected to cost between $255 and $265 million. Energy Trust of Oregon, Inc. contributed $6 million.[9]
Turbine output is around 600 VAC and converted to 34.5 kV by a transformer at the base of each tower. The output is gathered by a substation which combines the individual turbine contributions. Most collector cabling and associated control and monitoring fiber optic cable (up to 99 miles) is buried 3 feet (0.91 m) underground. Exceptions are made for aerial cables to span terrain such as canyons, wetlands, and cultivated areas to protect the environment. Up to 15 miles (24 km) of aerial cabling is permitted.[1] Bonneville Power Administration built a 12 mile 230 kV transmission line to collect the power. It has capacity for an expected additional 450 MW from two other proposed wind farms in Sherman County.[10]
The substation may be up to 6 acres including transformers, switching equipment, maintenance shops, control room, and offices.[1]
As many as ten meteorological observation towers up to 279 ft (85 m) are allowed throughout the wind farm to collect wind resource data.[1]
Notification to the Oregon Department of Energy is required if PGE chooses to install a turbine other than a General Electric 1.5 MW or 3.0 MW model.[1]
Construction must begin by June 30, 2009 and be completed by June 30, 2011.[1]
Visual impact restrictions are in force for the John Day Wildlife Refuge, John Day Wild and Scenic River, and the John Day State Scenic Waterway (from Parish Creek to Tumwater Falls). Wildlife protection must be provided for nesting bald eagles, peregrine falcons, Swainson's hawk, golden eagle, Burrowing owl, Ferruginous hawk and minimization of harm to other wildlife.[1]
Noise levels during construction and operation of the facility must not contribute more than 50 dBA at 24 identified noise sensitive sites.[1]
[edit] See also
[edit] References
- ^ a b c d e f g h i The Oregon Energy Facility Siting Council (May 10, 2007). Second Amended Site Certificate for the Biglow Canyon Wind Farm (PDF). Oregon Department of Energy. Retrieved on 2008-01-28.
- ^ Hill, Gail Kinsey. Wind farm in gorge may blow others away. The Oregonian. August 1, 2005.
- ^ Hill, Gail Kinsey. PGE power project rides on the wind. The Oregonian. April 12, 2006.
- ^ Hill, Gail Kinsey. PGE has the wind and adds the mills. The Oregonian. November 28, 2006.
- ^ a b c d Sickinger, Ted. Demand for wind dwarfs supply. The Oregonian, November 9, 2007.
- ^ a b PGE Completes Biglow Canyon Wind Farm. Renewable Energy Access. Retrieved January 28, 2008.
- ^ Siemens Energy to supply wind farm turbines. The Engineer Online. Retrieved April 4, 2008.
- ^ Confusingly, the power substation near The Dalles is named John Day substation. See Pacific Northwest-Pacific Southwest Intertie. US Bureau of Reclamation. Retrieved on 2008-01-28.
- ^ a b PGE press release (December 21, 2007). PGE's Biglow Canyon Wind Farm Helps Make Holiday Lights Greener. Yahoo. Retrieved on 2008-01-28.
- ^ Klondike III/Biglow Canyon Interconnection. Bonneville Power Administration (September 4, 2007). Retrieved on 2008-01-28.
[edit] External links
- Oregon DOE: all Oregon certificates for Biglow Canyon Wind Farm